The latest proposed version seems to be a 8.6 GW plant, which is supposed to meet 5% of the UK's needs (that would be roughly 20 TWh/year, or a capacity factor of around 25%). A single giant project, 1500 times bigger than the largest wind turbine; but it is not much overall - and not much even with all the other potential estuaries barraged.

The same amount of electricity would be produced by off-shore wind farms with a combined capacity of 5.7 GW, assuming a capacity factor of 40%. The cost to build that with all strings attached, even at today's increased prices is presently around £17 billion I believe (but Jérôme correct me).