Some new details on the mobile generator story, but without an ending:

TEPCO tardy on N-plant emergency : National : DAILY YOMIURI ONLINE (The Daily Yomiuri)

....tsunami destroyed 12 of the 13 emergency generators.

"Round up all the power-supply cars and send them to the plant right now!" shouted a TEPCO supervisor at the utility's head office in Tokyo.

...TEPCO dispatched power-supply vehicles from various power stations around the country to the crippled nuclear plant. However, the vehicles had to travel very slowly because of damage to roads in northeastern Japan. The first power-supply car did not reach the plant until 9 p.m. on March 11.

Once at the site, the lack of preparation became apparent. Cables needed to connect the vehicles' high-voltage electricity to plant facilities were not long enough. TEPCO immediately ordered additional cables, but precious time had been wasted. Power would not be restored at the plant by midnight.