Welcome to European Tribune. It's gone a bit quiet around here these days, but it's still going.
Display:
DSB wants to dump AnsaldoBreda - Politiken.dk

DSB has ordered lawyers to investigate how the Danish state railways service can get out of a contract with the Italian train producer AnsaldoBreda for IC4 trains that do not fulfil requirements.

Denmark ordered 83 IC4 trains from AnsaldoBreda in 2001, only 42 of which have been delivered and most of which have extensive technical problems.

"DSB doesn't believe that the DSB trains will ever run in the way they envisaged and certainly not to the extent envisaged. So we have to find out whether we can even expect them to run properly. Will they ever be able to fill the role envisaged when they were ordered," said Transport Minister Hans Christian Schmidt following a Transport Committee meeting.

by afew (afew(a in a circle)eurotrib_dot_com) on Thu May 12th, 2011 at 04:32:20 PM EST
[ Parent ]
This is now developing into the most disastrous rolling stock order in history.
  • These trains were originally ordered in December 2000, for delivery from March 2003 to July 2005.
  • The first unit was delivered to Denmark in autumn 2003, but only a second followed by the time the entire batch was supposed to have been delivered, and even their testing wasn't completed as they had several problems.
  • AnsaldoBreda was first forced to pay compensation in November 2005.
  • The first commercial run was in June 2007, with a single unit and as local train, but commercial runs ended after exhaust problems.
  • DSB first threatened to cancel the contract in its June 2008 ultimatum, demanding 15 functional sets within 12 months – at the time, they had 5 sets.
  • Commercial runs were started again in August 2008 (five years delay).
  • In May 2009, barely meeting the 15-functional-sets ultimatum from a yeare earlier, AnsaldoBreda again agreed to pay compensation, adding up to half of the original contract price(!). Also, a a new delivery schedule lasting until 2012 was agreed. By the new schedule, DSB was supposed to have 44 trains by the end of 2010, and 53 by the end of March.
  • At the time AnsaloBreda was still doing development work (!), making all deliveries unique and fault-prone.
  • DSB was in a bind over a cancellation of the program because government plans foresee mainline electrification from around 2020: if they dumped the IC4s and issued a big new diesel mutliple unit order for delivery in the middle of the 2010s, those trains would not have been amortised by the time DSB would have to buy new electric multiple units to replace them.

As noted before, I think this mess is a cascading result of AnsaldoBreda focusing its efforts on getting an also problematic electric locomotive delivered to Italian State Railways; and this mess also resulted in the delay of deliveries of Dutch-Belgian high-speed trains.

*Lunatic*, n.
One whose delusions are out of fashion.

by DoDo on Fri May 13th, 2011 at 04:18:12 AM EST
[ Parent ]

Display:

Occasional Series