BBC News - Wind power deadline sees US firms rush to build turbines

US energy companies are racing to install wind turbines before a federal tax credit expires at the end of this year.

Experts say that wind power has exceeded the construction of natural gas plants in recent months.

However the financial incentive for wind could be lost as congress struggles to avoid financial deadlock.

Even if the credit is extended it is expected that new installations will decline in 2013.

According to industry analysts, the federal government's production tax credit has played an important role in the expansion of wind energy across the US since it was first introduced in 1992.

At that point there was less than 1.5 gigawatts of power generating capacity provided by wind across the country. That figure has grown dramatically. This year has seen around 12 gigawatts of wind power capacity installed, outpacing even natural gas projects which have boomed on the back of cheap shale.

The government subsidy works out at 2.2 cents per kilowatt hour of power produced over ten years. This amounts to around $1m (£620,000) for every large turbine. However the deadline is absolute - to get the money the blades on new installations must be turning and generating power before the 31st of December.

"There's a lot of rushing right now to get projects completed by the end of the year," says Rob Gramlich, senior vice president at the American Wind Energy Association.

"It is not a great way to run a business with this policy-induced uncertainty."

by afew (afew(a in a circle)eurotrib_dot_com) on Tue Jan 1st, 2013 at 01:06:24 PM EST